Trade Specifications

The following Trade Specifications must be read in conjunction with all other Contract documentation including; Tender Letter, Operating Procedures for All Contractors, Conditions of Contract for Works, Labour Only and Purchase Orders, General Construction Notes (England & Wales), Suppliers and Sub Contract Works - SLA and the Company's Occupational Safety, Health & Environmental Management System.

Our aim is to enable our sub-contractors and suppliers to access key Commercial information such as Terms & Conditions, Trade Specification, etc. online as soon as they are updated and revised. We hope that this will ensure that our supply chain is always fully informed as quickly as possible.

Whilst available online, this information is also available from the Commercial Departments at our Divisional offices and will form part of any contract we place (as set out in the Order).

As part of the integration work which is now underway, you will see changes being incorporated into these Trade Specifications, in the near future, to include Redrow Homes specifications. Currently, where the Barratt Homes and David Wilson Homes logo's exist, these Trade Specifications are only applicable to these brands of Barratt Redrow plc.

Please be aware that bogus web sites seeking fees for the chance of working with major contractors exist.

Jon Hayward
Commercial Director (Group)

tagged "Roads and Sewers"

Roads & Sewers Stage 2

Revision N - 01.07.2024

Subsection 10.16 has added the note that all plant utilised on site shall be compliant with Non-Road Mobile Machinery regulations, and any other air quality requirements that may be enforced locally.

Subsection 10.20 Dealing with Spills has been amended from gully bags to re-usable silt traps.

Roads & Sewers to Binder Course inc. stage 2

Revision S - 01.07.2024

Subsection 10.16 has added the note that all plant utilised on site shall be compliant with Non-Road Mobile Machinery regulations, and any other air quality requirements that may be enforced locally.

Subsection 11.2 wording has been amended to remove the reference to gully pots filled with straw and include the contractor supplying and installing a proprietary re-usable silt trap system.